GFK ROHRE DN 2400 FÜR DAS KRAFTWERK EMSLAND
INSTALLATION OF A COOLING WATER LINE DN 2400
Alstom Power Systems is constructing a gas- and steam power plant for RWE AG in Lingen/Germany. Capacity: 876 MW.
TPR Fiberdur® GmbH & Co. KG was commissioned to install a cooling water line DN 2400 with sand-reinforced GRP-Pipes.
Scope of delivery: | • Installation |
• Prefabrication at site | |
• Installation of piping systems | |
including laminate connections |
Expertise, liability and proven experience in the field of installation of large bore glassfiber reinforced pipes in combination with project management capabilities were key factors for Fiberdur® to secure this order.
Customer: | ALSTOM POWER SYSTEMS | |
Operator: | RWE AG, Lingen, Germany | |
Service: | Underground cooling water line | |
5 bar operating pressure | ||
System: | GRP sand-filled Pipe DN 2400 | |
Joints: | Lamination at site | |
Constructed: | 2007-2008 | |
For further information please contact: | ||
Stephan Wipperfürth | ||
phone: 0049 2464 972 148 | ||