UDDEVALLA SWEDEN - WASTE-TO-ENERGY PLANT


CHP PRODUCING WASTE TO ENERGY PLANT
Uddevalla Energy is building a new CHP producing waste to energy plant with an annual capacitiy for thermal treatment of up to 100,000 tons of waste.
Fiberdur® received the order for the delivery and installation of approx. 2,500 m GRP pipes and more than 2,300 fittings for
• Process water | |
• SO2-Stage | |
• Condensing Stage | |
• NaOH-Stage | |
• WWTP-Stage | |
Scope of supply: | |
• Pipe and fittings | |
• Spool fabrication at site | |
• On site installation of piping systems | |
including valves and steel supports |
High product quality in combination with fast delivery times and flexibility were key factors for Fiberdur® to secure this turnkey order.
Customer: | Fisia Babcock Environment GmbH |
Operator: | Uddevalla Energy |
Diameter: | DN 25 - DN 400 |
System: | CSVE Vinylester pipe system |
for 10 bar service pressure | |
Joints: | adhesive bonded |
Constructed: | 2008 - 2009 |
| |
Wolfgang Keser | |
phone: 0049 2464 972 149 | |




