GHANNOUCH - TUNESIA 400 MW COMBINED CYCLE POWER PLANT
The Ghannouch Power Plant is located in South Tunisia, approx. 10 km in the North of Gabes. It is the second KA26 combined-cycle power plant in North Africa after "Terga" in Algeria.
The new plant will be erected in the area of the old power plant of Ghannouch thus allowing the use of existing commodities such as sea water intake and the discharge of waste water.
Fiberdur® received the order for the delivery of more than 1300 GRP pipes and 820 fittings DN 25 - DN 400.
Scope of supply: | Delivery of pipe systems |
DN 25 to DN 400 | |
Documentation |
The quality of our products, production time efficiency as well as our expert engineering support were the key factors for Fiberdur® to receive this job.
Customer: | ALSTOM Power Systems |
Operator: | Société Tunisienne de l'Electricité |
et du Gaz (STEG) | |
Service: | Cooling water lines |
System: | Vinylester PN 16/PN 10 |
Joints: | Adhesive bonding |
Constructed: | 2010 - 2011 |
| |
Stephan Wipperfürth | |
phone: 0049 2464 972 148 | |